UPDATE Important roadworks information: A12 northbound junctions 22 to 24 – resurfacing

Important roadworks information

A12 northbound junctions 22 to 24 – resurfacing

 

I am writing to tell you that we plan to carry out resurfacing works on the A12 between junctions 22 and 24. Once complete, drivers will benefit from a safer, smoother and better-defined road surface.

 

We plan to complete this work in four phases between Wednesday 29 January and Thursday 27 February 2025. We will work between 9pm and 5am on weeknights only, weather permitting.

 

  • Phase 1 – between 29 January and 1 February 2025
  • Phase 2 – between 6 February and 8 February 2025
  • Phase 3 – between 12 February and 15 February 2025
  • Phase 4 – between 26 February and 27 February 2025

 

Closures and diversions

To carry out the work safely, we will need to close the A12 between junctions 22 and 24, and divert traffic as detailed below:

 

  • Exit the A12 at junction 19 Boreham
  • Follow the A131 to Braintree and join the A120
  • Follow the A120 eastbound to Marks Tey
  • Rejoin the A12 at junction 25

 

A map of the diversion can be found below.

 

How to find out more

 

For the latest information, please visit our dedicated webpage: https://nationalhighways.co.uk/our-roads/east/east-road-maintenance-work/

 

If you would like more information, please contact us on 0300 123 5000, or by email at info@nationalhighways.co.uk.

 

Yours faithfully

 

Bev Gorani

Project Manager

Operations East, Scheme Delivery Team

 

 

This email may contain information which is confidential and is intended only for use of the recipient/s named above. If you are not an intended recipient, you are hereby notified that any copying, distribution, disclosure, reliance upon or other use of the contents of this email is strictly prohibited. If you have received this email in error, please notify the sender and destroy it.

National Highways Limited | General enquiries: 0300 123 5000 |National Traffic Operations Centre, 3 Ridgeway, Quinton Business Park, Birmingham B32 1AF | https://nationalhighways.co.uk | info@nationalhighways.co.uk

Registered in England and Wales no 9346363 | Registered Office: Bridge House, 1 Walnut Tree Close, Guildford, Surrey GU1 4LZ

Consider the environment. Please don’t print this e-mail unless you really need to.


Leave a Reply

Your email address will not be published. Required fields are marked *